Phase 1: 2000-2007

Phase 1 2000-2007

Intersection Improvements

  Project Description Capital Costs1
1 SR 7/SR 273 Addition of a second westbound left turn lane in the median of SR 273. Construction Summer 2000. $0.85
2 Walther Road/ Route 40 Addition of a southbound right turn lane to provide a shared left/through lane and a dedicated right turn lane. $0.35
3 Governor's Square/ Route 40/ Glendale Plaza Minor widening and restriping to provide southbound double left turn lanes, a southbound through lane, and a southbound right turn lane; northbound double left turn lanes, a northbound through lane, and a dedicated northbound right turn lane. (Tied to the Eden Square Connector.) $0.64
4 SR 72/Route 40 Addition of northbound and southbound through lanes and eastbound and westbound left turn lanes to provide double left turns. $1.14
5 Del Laws Road/SR 72 Realignment of the intersection to align with the proposed entrance for the Fox Run Business Center. The intersection will provide dedicated left, through and right lanes along SR 72 at the intersection. $0.71
6 Eden Square/Route 40 Channelization of turning movements from the southbound SR 1 exit ramp to Eden Square to eliminate weaving across Route 40. Construction summer 2000. $0.40
7 Buckley Boulevard/ Route 40 Installation of a signal and channelization. Construction summer 2000. $0.12
Subtotal $4.21

Interchanges/Grade Separations

  Project Description Capital Costs1
8 SR 1/Newtown Rd Interchange An extension of Newtown Road from SR 7 to and over SR 1, with an interchange at SR 1. Construction 2000-2002. $13.10

Arterial, Collector, and Local Road Improvements

  Project Description Capital Costs1
9 Church Road (Route 40 to Wynnfield) Reconstruction of Church Road to provide bike lanes and sidewalks along both sides. $5.45
10 SR 7 (Route 40 to Newtown Road) Addition of a second northbound and southbound through lane, bike lanes and sidewalks along both sides. Construction 2000-2001. $9.25
11 SR 7 (Newtown Road to SR 273) Addition of a second northbound and southbound through lane, bike lanes and sidewalks along both sides. $6.13
12 Reybold Road Reconstruction to provide bike lanes on both sides. $0.98
Subtotal $21.81

New Roads

  Project Description Capital Costs1
13 Eden Square Connector Construction of a new roadway from the intersection of SR 7 and the Glendale Connector to the Eden Square Shopping Center. $1.65
14 Rue Madora Drive Connection of the two existing sections of Rue Madora Drive. $0.60
Subtotal $2.25

Sidepaths

  Project Description Capital Costs1
  Route 40 (SR 72 to SR 1) Addition of sidepaths along both sides of Route 40. $11.65
  Old Baltimore Pike (SR 72 to SR 273) Addition of sidepath along one side of Old Baltimore Pike. First phase will be appropriate signing and pavement markings to convert the roadway shoulder for use as a bike lane tied to the Old Baltimore Pike planning study. $5.63
Subtotal $17.28

Sidewalks and Bike Lanes

  Project Description Capital Costs1
  SR 72 sidewalks (Route 40 to SR 71) Addition of sidewalks along both sides of SR 72. Tied to the SR 72 Corridor Study. $4.40
  Walther Road (Old Baltimore Pike to Route 40) Addition of sidewalks and bike lanes along both sides of the roadway. $2.56
  Porter Road (SR 896 to Route 40) Appropriate signing and pavement markings to convert the roadway shoulders for use as bike lanes. (To be done as part of Porter Road Reconstruction.) $0.07
  Wilton Boulevard and Appleby Road Addition of sidewalks along both sides of both roadways. $2.45
  Songsmith Drive (McMullen Circle to Smalleys Dam Road) Addition of sidewalks along both sides of the roadway. $1.36
Subtotal $10.84

Pedestrian Improvements

  Project Description Capital Costs1
 
  • SR 72
  • Rickey Blvd
  • Scotland Dr
  • Glasgow Dr
  • Salem Church Rd
  • Eden Square
Short Term Improvements Project - Addition of various features at intersections on Route 40 to benefit the safety of pedestrians such as refuge islands, pedestrian signals, and median channelization. Construction summer 2000. $0.75

Transit Improvements

  Project Description Capital Costs1
  Enhancements to current transit service Purchase of additional buses to supplement the existing service in the corridor to support DART operational changes currently planned. $0.59
  Route deviation service along Route 40 Funding of a pilot project for route deviation service as an extension of the proposed neighborhood service. $1.55
  Additional pedestrian connections to transit Construction of sidewalk connections to provide transit customers with connections to bus stops. $0.30
  Additional bus stop improvements Addition of bus shelters at selected stops throughout the Corridor. $0.60
  Preservation and expansion of park and ride capacity in the corridor Preservation of the two existing park and ride lots at SR 7/SR 273 and in People's Plaza. Also, additional park and ride lots will be considered at the SR 72/Route 40 intersection and in the SR 7/Route 40 area. $1.10
  Waterford pedestrian access to Route 40 bus stop Construction of an ADA accessible bus stop, opposite Brookmont Drive, for the residents of Waterford. $0.29
Subtotal $4.43

Access Management

  Project Description Capital Costs1
  Access management on selected developed properties Inter-parcel connections, joint access, restriction of access, or other means to reasonably reduce the number of access points on Route 40. $0.83
  Access management on properties as they are developed or redeveloped Efforts in conjunction with the Site Review Team to identify potential for access management early in the development process. $0.05
Subtotal $0.88

Other Improvements

  Project Description Capital Costs1
  Landscaping, streetscaping and signing along Route 40 The details of this project are under consideration, but are likely to include overhead street name signs, landscaping, and lighting. $2.68

Planning Studies

  Project Description Capital Costs1
  Pleasant Valley Road/Frazer Road realignment This project includes studying the feasibility of realigning either Pleasant Valley Road, Frazer Road or both to combine the two intersections into one.  
  Newtown Road transportation corridor This project includes studying the potential options for the reserved right of way set aside for Newtown Road.  
  Old Baltimore Pike This project includes studying the future needs for this corridor, including sidepaths.  
  Glasgow Avenue "Main Street" This project includes studying potential options for old SR 896 in Glasgow.  
  Route 13 Corridor Study, SR 1 to Wilmington This project includes studying the future needs for this corridor.  
  SR 72 Corridor Study, Route 40 to SR 1 This project includes studying the future needs for this corridor.  
  SR 71 Corridor Study, SR 896 to Route 13 This project includes studying the future needs for this corridor.  
Subtotal $2.90

Plan Management

    Land use monitoring, traffic monitoring, trigger implementation, and Corridor Monitoring Committee involvement. $0.80

Concept Design

    Preliminary engineering costs for all triggered projects in Phases II and III. $2.85
Phase I Total $84.78

Notes:

1 - Costs in millions (1999 dollars). All costs include preliminary engineering, construction, right-of-way acquisition, and ITMS improvements.

2 - Sidepath: A pathway designated for pedestrians and bicyclists that is physically separated from traffic by an open space or barrier. A sidepath is at least 10' wide.

3 - Access Management: Access management limits and/or removes the number of points at which a vehicle may enter or exit a highway. It may include combining entrances and parking lots and adding service roads.

Scheduling and scope of projects is based on the Project Team's best estimate and is subject to change based on results of monitoring