Project Limits:

100' north and south of the center of the bridge

Project Need:

The bridge consists of 3 corrugated pipes with sack concrete headwalls. The pipes have significant corrosion and has been selected by the Pontis Bridge Management System for work. The bridge was deemed structurally deficit by DelDOT's Bridge Management Section. Due to the deficiency rating, a project to replace this structure has been initiated.

Project Overview:

This project involves complete replacement of the existing structure. The existing pipes will be replaced with a 10'x 5' precast concrete box culvert. Riprap will be placed upstream and downstream of the new structure for scour protection. Also included is 200' of new pavement.

Project Timeline:

Design Phase:

Design work completed January 2018

Construction Phase:

Construction work to be completed September 2018