INFORMATION

Project Limits:

Approximately 300 feet west and 100 feet east of the bridge.

Project Need:

The Old SR 24 bridge is a multi-span bridge. The structure consists of wood piles with lateral bracing, wood beams, a reinforced concrete deck, and wooden railings. Each of these elements are significantly degraded from tidal forces, marine borer activity, and general degradation that occurs over time. This bridge has been deemed structurally deficient by DelDOT's Bridge Management Section and as a result a project has been initiated to repair this bridge.

Project Overview:

The Old SR 24 bridge over Love Creek is to be removed.

Project Timeline:

Design Phase:

Design work to be completed no later than Summer of 2018.

Construction Phase:

Construction work to be completed no later than Spring 2019.