Project Limits:
Approximately 250 feet east and west of the bridge along Nine Foot Road
Project Need
There is significant corrosion at the waterline with 100% section loss at several locations throughout the pipes. The existing pipes are structurally deficient and were selected by the Pontis Bridge Management System for work.
Project Overview:
Replace the existing two corrugated aluminum pipes with a precast box culvert. Place riprap for scour protection. Reconstruct approaches and place guardrail as necessary. Work will be performed under a full road closure with detour for traffic.
Project Timeline:
Design Phase:
Design work to be completed no later than Summer, 2018.
Construction Phase:
Construction work to be completed no later than Spring, 2019.