Project Limits:

Chapman Road and BR 1-714 from Regal Blvd to Galleon Drive

Project Need:

Deterioration of the existing concrete deck has caused the bridge to become structurally deficient. There is spalling, delamination, and cracking of the piers and abutments. There is significant corrosion and section loss of the steel especially under the open joints.

Project Overview:

This project involves the replacement of Bridge 1-714. The scope of work is to replace the existing bridge with a new one. The new bridge will be constructed adjacent and just to the north of the existing bridge. The new bridge will consist of two spans over NB and SB I-95 with a wall supported embankment across the median. The new bridge will include a full width sidewalk and shoulders to carry pedestrian and bike traffic.

Project Timeline:

Design Phase:

Design work to be completed no later than Spring 2019

Construction Phase:

Construction work to be completed Summer 2021

Additional Comments

Traffic will be maintained on the existing bridge while the new bridge is constructed adjacent to it.