INFORMATION

Project Limits:

200 feet north and south of bridge

Project Need

This bridge consists of severely corroded corrugated metal pipes (CMPs). As such, it was structurally deficient and was selected by the Pontis Bridge Management System for replacement

Project Overview:

Replaced the deteriorated CMPs with a precast concrete frame. Construction completed in one stage with a detour. Reconstructed approaches and placed a scour countermeasure in the stream to protect the structure.

Current Project Schedule:

Design Phase:

Design work completed in October 2011.

Construction Phase:

Construction completed, June 2012