INFORMATION

(Construction began November 2003)
(Traffic shifted to temporary 6-lane road in July 2004)

Improvements include:

  • Construction of two new underpasses of US 202 at both East Park Drive and Foulk Road/ SR 141 Spur
  • Weldin Road to be relocated to intersect with Foulk Road
  • Six-lane temporary road to be converted into the permanent two-lane West Park Drive (video)
  • Landscaping along US 202

View Detail (pdf file 793kb) of area.