January 2002

Advertise construction contract

2002 Spring/Summer

Close Rockland Road at US 202
Note: Rockland Road will reopen when West Park Drive is converted to a final 2-lane design in next construction contract

Clear and grub project site

Establish maintenance and protection of traffic

Prepare construction staging areas

Construct and install erosion and sedimentation controls

Begin installation of utilities

Excavate for temporary roadway

Begin installation of Rockland Road and SR 141 spur culverts at Alapocas Run

Begin stream restoration of Alapocas Run

2002 Summer/Fall

Above operations continue as required

Complete construction of stormwater management facilities

Complete installation of culverts at Rockland Road and SR 141

Complete stream restoration of Alapocas Run

Begin building the wetland mitigation site

Begin construction of temporary road embankment

Begin construction of pedestrian/bike path

Begin installation of landscaping

2002-03 Winter/Spring

Above operations continue as required

Complete building of wetland mitigation site

Complete construction of temporary road embankment

Complete construction of pedestrian/bike path

Complete installation of utilities

Install final landscaping features

Pave temporary roadway