INFORMATION

Project Limits:

200 feet north and south of the bridge

Project Need:

The existing pipes are structurally deficient and were selected by the Pontis Bridge Management System for work. It has a sufficiency rating of 69.3 and This bridge is ranked 24th on 2013 DelDOT Bridge Deficiency List. There is corrosion at the waterline with 100% section loss at some locations.

Project Overview:

This project involves the replacement of a large corrugated metal pipe arche with reinforced concrete pipes. The approach roadways and guardrail will be reconstructed as needed and riprap will be placed in the stream for scour protection. The work will be performed under a full road closure with a detour.

Project Timeline:

Design Phase:

Design work completed August 2017.

Construction Phase:

Actual Start Date - June 11, 2018
Actual Substantial Completion Date - August 22, 2018

(Reviewed and Updated on 10/19/2018)