Bookmark and Share
Project Information [T201404401]

This information is updated nightly.
Recently awarded projects may not contain the awarded contractor or bid amount information.
This information can be found at the bottom of the bid tabulation report, which is updated as projects are awarded.

Project Information
Project Number
T201404401
Project Title
GOVERNOR PRINTZ BOULEVARD RESTORATION
Description
Restoration of Governor Printz Boulevard within the limits of the NCC Sewer project ,from north of Cauffiel Parkway to Rolling Road.
Justification
The project is being constructed through an agreement with New Castle County to restore Governor Printz Boulevard to its condition prior to NCC's Sewer Project.
Advertise Date
10/11/2013
Bid Amount
$687,628.91
Bids Received Date
10/25/2013
Bid Tabulation Report
View PDF Report
Date Awarded
10/30/2013
Total Project Cost
$1,222,049.40
First Chargeable Day
11/18/2013
Contractor
DIAMOND MATERIALS LLC
Estimated Completion Date
12/09/2013
Bond Information
No bond information is available.
Payment Information
Est No Header Detail Status Est Amt Payment Type Advice No Advice Date
1 [View] [View] Interim $667,664.18 EFT 287858 01/08/2014
2 [View] [View] Interim $337,761.12 EFT 301559 02/25/2014
3 [View] [View] Semi-final $74,661.78 EFT 357693 09/09/2014

[Back to Search]