Project Information [T201347202]

This information is updated nightly.
Recently awarded projects may not contain the awarded contractor or bid amount information.
This information can be found at the bottom of the bid tabulation report, which is updated as projects are awarded.

Project Information
Project Number
T201347202
Project Title
BR 3-463 ON S396 WEST LINE ROAD OVER BUNTINGS BRANCH (EMERGENCY REPLAC
Description
This project involves the replacement of the existing corrugated metal pipes with a precast concrete frame at BR 3-463. Additional work includes minor reconstruction of the approach roadway, installation of guardrail as needed, and placement of riprap in the stream to prevent scour. The work will be performed under a full road closure with detour.
Justification
As a result of Hurricane Sandy, the existing corrugated metal pipes failed and the road experienced significant erosion. The existing structure will most likely not survive another storm event.
Advertise Date
03/11/2013
Bid Amount
$223,708.60
Bids Received Date
03/26/2013
Bid Tabulation Report
View PDF Report
Date Awarded
04/09/2013
Total Project Cost
$331,510.73
First Chargeable Day
06/04/2013
Contractor
MUMFORD & MILLER CONCRETE INC
Actual Completion Date
07/26/2013
Bond Information
No bond information is available.
Payment Information
Est No Header Detail Status Est Amt Payment Type Advice No Advice Date
1 [View] [View] Interim $32,170.70 EFT 246603 07/30/2013
2 [View] [View] Interim $142,726.95 EFT 246603 07/30/2013
3 [View] [View] Interim $48,539.50 EFT 253175 08/27/2013
4 [View] [View] Semi-final $9,514.71 EFT 304856 03/10/2014
5 [View] [View] Semi-final $2,973.00 EFT 337467 06/18/2014