Project Information [T201206204]

This information is updated nightly.
Recently awarded projects may not contain the awarded contractor or bid amount information.
This information can be found at the bottom of the bid tabulation report, which is updated as projects are awarded.

Project Information
Project Number
T201206204
Federal Aid Number
ESTP-2012(24)
Project Title
PAVEMENT & REHABILITATION, SOUTH I-IV, 2012
Description
PATCHING, MILLING AND OVERLAY.
Justification
POOR PAVEMENT CONDITION.
Advertise Date
01/28/2013
Bid Amount
$1,962,188.58
Bids Received Date
02/26/2013
Bid Tabulation Report
View PDF Report
Date Awarded
03/13/2013
Total Project Cost
$2,429,768.59
First Chargeable Day
07/01/2013
Contractor
DIAMOND MATERIALS LLC
Estimated Completion Date
01/02/2013
Bond Information
No bond information is available.
Payment Information
Est No Header Detail Status Est Amt Payment Type Advice No Advice Date
1 [View] [View] Interim $102,097.04 EFT 254217 08/30/2013
2 [View] [View] Interim $175,890.59 EFT 259998 09/23/2013
3 [View] [View] Interim $1,283,864.01 EFT 269139 10/24/2013
4 [View] [View] Interim $33,480.00 EFT 269926 10/28/2013
5 [View] [View] Interim $112,461.04 EFT 279161 12/02/2013
6 [View] [View] Interim $4,642.12 EFT 295247 02/04/2014