SR2 and Upper Pike Creek Road

Project Name

Kirkwood Highway and Upper Pike Creek Road/Old Harmony Road Intersection Improvements

Project Limits

Kirkwood Highway from Harmony Road to Green Valley Circle

Project Need

The intersection of Kirkwood Highway and Upper Pike Creek Road/Old Harmony Road was recommended for improvements in the Highway Safety Improvement Program (HSIP). Limited sight distance for left-turning vehicles is causing high crash rates at this intersection.

Project Overview

In order to address the safety issues at this intersection, we are proposing to close the median and provide left-turn access to Upper Pike Creek Road and Old Harmony Road through u-turns at the signalized intersections of Green Valley Circle and Harmony Road.

Project Schedule

Anticipated/Actual Start Date
April 2011
Anticipated/Actual Completion Date
July 2011
Current Construction Schedule
We anticipate that construction will begin in the spring of 2010 and will take four months to complete.
Contractor & Cost
The project was awarded to A-Del Construction.  A-Del submitted a bid of $449,648.15
Construction Details
TBD
Detailed Description
The proposed improvements include closing the median on Kirkwood Highway at Upper Pike Creek Road/Old Harmony Road, lengthening the left-turn lanes at Harmony Road and Green Valley Circle, and modifying the signal timing.
PROJECT INFORMATION
 
 
PUBLIC FEEDBACK
Public Relations This link opens an email client
302.760.2080
800.652.5600 (DE only)

Matthew Vincent This link opens an email client
Project Manager
302.760.2746
 
 
 