Project Limits:

200 feet north and south of bridge

Project Need:

This bridge consists of severely corroded corrugated metal pipe arches (CMPA). The roadway has been closed due to the failure of one of the pipe arches. As such, it is structurally deficient and was selected by the Pontis Bridge Management System for work.

Project Overview:

Replace the deteriorated CMPs with a precast concrete frame. Construction will be completed in one stage with a detour. Reconstruct approaches and place guardrail as required. Place a scour countermeasure in the stream to protect the structure.

Project Timeline:

Road Closed:

February 21, 2010

Design Phase:

The design phase was completed on August 31, 2010.

Construction Phase:

Construction began in early January, 2011 and is estimated to take 82 days, weather permitting.

PROJECT INFORMATION
 
 
PUBLIC FEEDBACK
Public Relations This link opens an email client
302.760.2080
800.652.5600 (DE only)

Jason N. Hastings, P.E. This link opens an email client
Project Manager
302.760.2310
 
 
 
Last Updated: Friday, 11-Feb-2011 09:55:45 Eastern Standard Time
site map   |   about this site   |    contact us   |    translate   |    delaware.gov