Construction Timeline - as of 7/14/11
Design Bridge: 2008 - 2009
Mobilization: Winter 2008 - Summer 2009
Foundations/Concrete Piles: Winter 2008 - Summer 2009
Footings: Summer 2009 - Fall 2009
Substructure Abutments / Piers For Bridge Approaches: Summer 2009 - Fall 2009
Pylons: Summer 2009 - Summer 2010
Bridge Approach Spans: Winter 2009 - Winter 2010
Cable Supported Superstructure on Falsework: Fall 2009 - Late 2010
Cable Stay Installation: Summer 2010 - Fall 2011
Bridge Open to Traffic: Late 2011
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 

 

 

 