Blue Ball Properties - News & Updates - West Side Improvements - Broad Schedule

January 2002 Advertise construction contract
   
2002 Spring/Summer Close Rockland Road at US 202
Note: Rockland Road will reopen when West Park Drive is converted
to a final 2-lane design in next construction contract
  Clear and grub project site
  Establish maintenance and protection of traffic
  Prepare construction staging areas
  Construct and install erosion and sedimentation controls
  Begin installation of utilities
  Excavate for temporary roadway
  Begin installation of Rockland Road and SR 141 spur culverts at Alapocas Run
  Begin stream restoration of Alapocas Run
   
2002 Summer/Fall Above operations continue as required
  Complete construction of stormwater management facilities
  Complete installation of culverts at Rockland Road and SR 141
  Complete stream restoration of Alapocas Run
  Begin building the wetland mitigation site
  Begin construction of temporary road embankment
  Begin construction of pedestrian/bike path
  Begin installation of landscaping
   
2002-03 Winter/Spring Above operations continue as required
  Complete building of wetland mitigation site
  Complete construction of temporary road embankment
  Complete construction of pedestrian/bike path
  Complete installation of utilities
  Install final landscaping features
  Pave temporary roadway
 
PUBLIC FEEDBACK
The Blue Ball Properties team invites public and media inquiries about this project. We can make community presentations, set-up a display, provide technical information, and answer individual questions.
Robert King This link opens an email client
Community Relations Officer
302.760.2349
800.652.5600
P.O. Box 778 Dover DE 19903
 
 
 
Last Updated: Monday, 04-Aug-2008 08:52:20 Eastern Daylight Time
site map   |   about this site   |    contact us   |    translate   |    delaware.gov