Advertise construction contract |
| |
|
| 2002 Spring/Summer |
Close Rockland Road at US 202 Note: Rockland Road will reopen when West Park Drive is converted to a final 2-lane design in next construction contract |
| |
Clear and grub project site |
| |
Establish maintenance and protection of traffic |
| |
Prepare construction staging areas |
| |
Construct and install erosion and sedimentation controls |
| |
Begin installation of utilities |
| |
Excavate for temporary roadway |
| |
Begin installation of Rockland Road and SR 141 spur culverts at Alapocas Run |
| |
Begin stream restoration of Alapocas Run |
| |
|
| 2002 Summer/Fall |
Above operations continue as required |
| |
Complete construction of stormwater management facilities |
| |
Complete installation of culverts at Rockland Road and SR 141 |
| |
Complete stream restoration of Alapocas Run |
| |
Begin building the wetland mitigation site |
| |
Begin construction of temporary road embankment |
| |
Begin construction of pedestrian/bike path |
| |
Begin installation of landscaping |
| |
|
| 2002-03 Winter/Spring |
Above operations continue as required |
| |
Complete building of wetland mitigation site |
| |
Complete construction of temporary road embankment |
| |
Complete construction of pedestrian/bike path |
| |
Complete installation of utilities |
| |
Install final landscaping features |
| |
Pave temporary roadway |
|
|